nd.gov - The Official Portal for North Dakota State Government
North Dakota: Legendary. Follow the trail of legends

North Dakota State Public Service Commission

Public Service Commission

Quick Links

Case PU-24-361 Detail

10/24/2024

345kV Mercer-McLean-Ward-Mountrail-Williams Cty
Siting Application
Electric

Entities:

Basin Electric Power Cooperative

65 Dockets:

[Hide | Show]
65
Rows
Docket
Number
Description & Type Page
Count
On Behalf Of Filed By Date
Filed
1 1 Consolidated Application for a Certificate of Corridor Compatibility & Route Permit and USB Drive Containing GIS Files - Redacted
Application
583 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2024.10.24
2 2 Receipt# 12,226 $100,000.00 Application Fee
Receipt
1 Basin Electric Power Cooperative 2024.11.22
3 3 Receipt# 12,227 $50,000.00 Siting Admin Fee
Receipt
1 Basin Electric Power Cooperative 2024.11.22
4 4 Siting Admin Fee
Other
4 Public Service Commission 2024.11.25
5 5 Request for ALJ
Other
3 Public Service Commission 2025.01.14
6 6 Letter Designating Administrative Law Judge
Letter
1 Office of Administrative Hearings Hope Hogan, Director 2025.01.17
7 7 Notice of Filing and notice of Public Hearing
Notice
3 Public Service Commission 2025.01.30
8 8 Affidavit of Service by Certified Mail - Notice of Filing and Notice of Public Hearing
Affidavit
4 Public Service Commission 2025.01.31
9 9 Affidavit of Service by Regular & Electronic Mail - Notice of Filing and Notice of Public Hearing
Affidavit
9 Public Service Commission 2025.01.31
10 10 Email to/From NDNA re Publication of Notice
Other
4 North Dakota Newspaper Association (NDNA) 2025.01.31
11 11 Return Receipt (2)
Other
2 United States Postal Service 2025.02.06
12 12 Letter Indicating Court Reporter to Attend Hearing
Letter
2 Basin Electric Power Cooperative Maggie Olson, Sr Staff Counsel 2025.02.14
13 13 Letter Enclosing Pre-Filed Testimony of Bobby Nasset, Philip Westby, Ryan King, & Nathan Kleyer and Nine Exhibits
Other
228 Basin Electric Power Cooperative Maggie Olson, Sr Staff Counsel 2025.02.19
14 14 Agency Comments
Other
1 State Historical Society of North Dakota (SHS) Willam Peterson 2025.02.21
15 15 Agency Comments
Other
3 North Dakota Department of Environmental Quality (DEQ) Karl Rockerman 2025.02.21
16 16 Petition to Intervene
Other
7 Braaten Law Firm by John Bartelson,by Derrick Braaten 2025.02.21
17 17 Updated Appendix A
Other
70 Basin Electric Power Cooperative 2025.02.21
18 18 Order Granting Petition to Intervene
Order
4 Hope Hogan, ALJ - Office of Administrative Hearings 2025.02.26
19 19 Letter Enclosing Witness List, Exhibit List, Attendance Sheet, and Hearing Recording
Letter
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.03
20 20 Witness List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.03
21 21 Exhibit List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.03
22 22 Attendance Sheet
Other
3 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.03
23 23 Electronic Recording of 26 February 2025 Formal Hearing
Audio
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.03
24 24 Memorandum
Memo
1 Public Service Commission Victor Schock 2025.03.05
25 25 Notice of Public Hearings
Notice
3 Public Service Commission 2025.03.05
26 26 Affidavit of Service by Certified Mail - Notice of Public Hearings
Affidavit
4 Public Service Commission 2025.03.05
27 27 Affidavit of Service by Regular & Electronic Mail - Notice of Public Hearings
Affidavit
9 Public Service Commission 2025.03.05
28 28 Email to/from NDNA re Publication of Notice
Other
9 Public Service Commission 2025.03.06
29 29 Return Receipt (2)
Other
2 United States Postal Service 2025.03.10
30 30 Return Receipt
Other
1 United States Postal Service 2025.03.11
31 31 Notice of Appearance of Wade C. Mann
Notice
2 Basin Electric Power Cooperative Wade C. Mann, Crowley Fleck, PLLP 2025.03.11
32 32 Notice of Prehearing Conference
Notice
3 Office of Administrative Hearings Hope L Hogan 2025.03.13
33 33 NDNA Invoice No. 14745 $1,533.74
Invoice
1 North Dakota Newspaper Association (NDNA) 2025.03.19
34 34 Affidavit of Publication With Tear Sheets
Affidavit
5 North Dakota Newspaper Association (NDNA) 2025.03.19
35 35 Letter Enclosing Stipulation and Proposed Order for Intervenor Withdawl
Other
7 Braaten Law Firm by John Bartelson,by Derrick Braaten 2025.03.26
36 36 Order Granting Withdrawl 2 Hope Hogan, ALJ - Office of Administrative Hearings 2025.03.28
37 37 Letter Enclosing Witness List, Updated Exhibit List, Exhibits 15, Attendance Sheet, & Hearing Recording
Letter
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.02
38 38 Witness List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.02
39 39 Updated Exhibit List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.02
40 40 Attendance Sheet
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.02
41 41 Electronic Recording of 31 March 2025 Formal Hearing
Audio
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.02
42 42 Agency Correspondence
Letter
2 North Dakota Department of Water Resources (DWR) Kyle Yrkoski, Planner III 2025.04.03
43 43 Letter Enclosing Witness List, Updated Exhibit List, Exhibits 1-9, 11-14 and 16-17, Attendance Sheet and Hearing Recording
Letter
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.08
44 44 Witness List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.08
45 45 Updated Exhibit List
Other
2 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.08
46 46 Attendance Sheet (2 pages)
Other
2 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.08
47 47 Electronic Recording of 04 April 2025 Formal Hearing
Audio
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.04.08
48 48 Exhibit 1 - LOS to Tande 345-kV Transmission Project Overview Map
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
49 49 Exhibit 2 - Crane Creek Substation Site Transmission Interconnection Plan Map
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
50 50 Exhibit 3 - LOS to Tande - LOS to Logan 345-230-kV Double-Cricuit Map
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
51 51 Exhibit 4 - Crank Creek to Satterthwaite 345-115-kV Segment Map
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
52 52 Exhibit 5 - 345-kV Single Circuit Structure Diagram
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
53 53 Exhibit 6 - 345-230-kV Double Circuit Tangent Structure Diagram
Exhibit
2 Basin Electric Power Cooperative 2025.04.08
54 54 Exhibit 7 - 2021 ITP Assessment Report
Exhibit
157 Basin Electric Power Cooperative 2025.04.08
55 55 Exhibit 8 - SPP Notification to Construct 210652
Exhibit
10 Basin Electric Power Cooperative 2025.04.08
56 56 Exhibit 9 - LOS to Tande 345-kV Transmission Project - Route Overview Maps
Exhibit
6 Basin Electric Power Cooperative 2025.04.08
57 57 Exhibit 10 - Application (PSC Dkt #1)
Exhibit
582 Basin Electric Power Cooperative 2025.04.09
58 58 Exhibit 11 - Pre-filed Testimony of Bobby Nasset
Exhibit
15 Basin Electric Power Cooperative 2025.04.08
59 59 Exhibit 12 - Pre-filed Testimony of Phillip Westby
Exhibit
8 Basin Electric Power Cooperative 2025.04.08
60 60 Exhibit 13 - Pre-filed Testimony of Ryan King
Exhibit
16 Basin Electric Power Cooperative 2025.04.08
61 61 Exhibit 14 - Pre-filed Testimony of Nathan Kleyer
Exhibit
11 Basin Electric Power Cooperative 2025.04.08
62 62 Exhibit 15 - Certificate Relating to Order Provisions Transmission Facility Siting
Exhibit
8 Basin Electric Power Cooperative 2025.04.02
63 63 Exhibit 16 - Right-of-Way Acquisition Summary (4-3-25)
Exhibit
1 Basin Electric Power Cooperative 2025.04.08
64 64 Exhibit 17 - Trust Lands Letter dated 3-14-25
Exhibit
1 Basin Electric Power Cooperative 2025.04.08
65 65 Letter Enclosing Proposed Findings of Fact, Conclusions of Law and Order, and NDSHPO Correspondence dated April 3, 2025
Other
10 Basin Electric Power Cooperative Maggie Olson, Sr. Staff Counsel 2025.04.09

Back to Top ↑

Event History:

4
Rows
Event Date & Time
1 Formal Hearing 2025.04.04 09:00 am
2 Formal Hearing 2025.03.31 01:00 pm
3 Formal Hearing 2025.03.06 09:00 am
4 Formal Hearing 2025.02.26 10:00 am