03/05/2025

Bison Generation Station - Williams County
Siting Application
Electric

Entities:

Basin Electric Power Cooperative

58 Dockets:

[Hide | Show]
58
Rows
Docket
Number
Description & Type Page
Count
On Behalf Of Filed By Date
Filed
1 9 Affidavit of Service by Certified Mail - Notice of Filing and Notice of Public Hearing
Affidavit
3 Public Service Commission 2025.05.09
2 10 Affidavit of Service by Regular & Electronic Mail - Notice of Filing and Notice of Public Hearing
Affidavit
8 Public Service Commission 2025.05.09
3 41 Affidavit of Publication With Tear Sheets
Affidavit
4 North Dakota Newspaper Association (NDNA) 2025.07.03
4 47 Affidavit of Service by Certified Mail - Findings of Fact, Conclusions of Law and Order
Affidavit
17 Public Service Commission 2025.08.08
5 1 Application for Certificate of Site Compatibility
Application
345 Basin Electric Power Cooperative Todd Brickhouse, CEO & General Manager 2025.03.05
6 27 Electronic Recording of 30 June 2025 Formal Hearing
Audio
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
7 28 Exhibit 1 - Combined-Cycle Illustration (Dkt #16)
Exhibit
1 Basin Electric Power Cooperative 2025.07.03
8 29 Exhibit 2 - BGS Location Map (Dkt #16)
Exhibit
1 Basin Electric Power Cooperative 2025.07.03
9 30 Exhibit 3 - BGS Visual Simulations (Dkt #16)
Exhibit
2 Basin Electric Power Cooperative 2025.07.03
10 31 Exhibit 4 - SPP System Seasonal Load & Capability Graph (Dkt #16)
Exhibit
1 Basin Electric Power Cooperative 2025.07.03
11 32 Exhibit 5 - Sound Level Contours Map (Dkt #16)
Exhibit
1 Basin Electric Power Cooperative 2025.07.03
12 33 Exhibit 6 - Pre-Filed Testimony of Chris Bauer (Dkt #16)
Exhibit
18 Basin Electric Power Cooperative 2025.07.03
13 34 Exhibit 7 - Pre-Filed Testimony of Benjamin Hertz (Dkt #16)
Exhibit
8 Basin Electric Power Cooperative 2025.07.03
14 35 Exhibit 8 - Pre-Filed Testimony of Erin Fox Dukart (Dkt #16)
Exhibit
13 Basin Electric Power Cooperative 2025.07.03
15 36 Exhibit 9 - Certification Relating to Order Provisions Energy Conversion Facility Siting
Exhibit
6 Basin Electric Power Cooperative 2025.07.03
16 37 Exhibit 10 - Application (Dkt #1)
Exhibit
345 Basin Electric Power Cooperative 2025.07.03
17 38 Exhibit 11 - Public Testimony Handouts
Exhibit
38 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
18 40 NDNA Invoice No. 14931 $696.24
Invoice
1 North Dakota Newspaper Association (NDNA) 2025.07.03
19 6 Letter Designating Administrative Law Judge
Letter
1 Office of Administrative Hearings Hope L. Hogan, Director 2025.04.16
20 13 Letter Indicating Court Reporter to Attend Hearing
Letter
1 Basin Electric Power Cooperative Maggie Olson, Senior Staff Counsel 2025.05.27
21 14 Agency Correspondence
Letter
3 North Dakota Department of Environmental Quality (DEQ) Karl Rockeman, P.E., Deputy Director 2025.06.05
22 17 Agency Correspondence
Letter
1 State Historical Society of North Dakota (SHS) William Peterson, Director 2025.06.23
23 18 Agency Correspondence
Letter
1 State Historical Society of North Dakota (SHS) William Peterson, Director 2025.06.23
24 19 Agency Correspondence
Letter
1 State Historical Society of North Dakota (SHS) William Peterson, Director 2025.06.23
25 20 Agency Correspondence
Letter
1 State Historical Society of North Dakota (SHS) William Peterson, Director 2025.06.23
26 22 Army Corps of Engineers Letter Dated 4-10-25
Letter
2 Basin Electric Power Cooperative 2025.06.26
27 23 Letter Enclosing Witness List, Updated Exhibit List, Attendance Sheet, Hearing Audio and Exhibits 9 and 11
Letter
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
28 50 Letter Closing OAH File
Letter
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.08.14
29 52 Letter Enclosing Executed Contract
Letter
14 Public Service Commission 2025.08.18
30 21 Memorandum
Memo
2 Ackerman-Estvold 2025.06.23
31 7 Commission Motion to Deem Application Complete and Issue a Notice of Filing and Notice of Public Hearing
Motion
1 Public Service Commission 2025.05.08
32 45 Commission Motion to Adopt the Findings of Fact, Conclusions of Law and Order
Motion
1 Public Service Commission 2025.08.07
33 8 Notice of Filing and Notice of Public Hearing
Notice
2 Public Service Commission 2025.05.08
34 46 Findings of Fact, Conclusions of Law and Order
Order
15 Public Service Commission 2025.08.07
35 4 Siting Admin Fee
Other
3 Public Service Commission 2025.03.10
36 5 Request for ALJ
Other
3 Public Service Commission 2025.04.14
37 11 Email to/from NDNA re Publication of Notice
Other
2 North Dakota Newspaper Association (NDNA) 2025.05.12
38 12 Return Receipt (2)
Other
2 United States Postal Service 2025.05.16
39 15 Email to/from NDNA Re Additional Publication of Notice for June 21, 2025 as requested by Basin Electric Power Cooperative
Other
3 North Dakota Newspaper Association (NDNA) 2025.06.10
40 16 Letter Enclosing Pre-Filed Testimony and Pre-Filed Exhibits 1-5
Other
46 Basin Electric Power Cooperative Maggie Olson, Sr. Staff Counsel 2025.06.16
41 24 Witness List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
42 25 Updated Exhibit List
Other
1 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
43 26 Attendance Sheet (4pages)
Other
4 Hope Hogan, ALJ - Office of Administrative Hearings 2025.07.03
44 39 Response to Request for Additional Information
Other
2 Basin Electric Power Cooperative Erin Fox Dukart, Director, Envir. Svcs. 2025.07.03
45 42 Proposed Findings of Fact, Conclusions of Law and Order
Other
9 Basin Electric Power Cooperative Maggie Olson, Sr. Staff Counsel 2025.07.08
46 43 June 30, 2025 Formal Hearing Transcript (Full and Condensed)
Other
261 Emineth & Associates Court Reporters Stephanie A. Smith, Reg. Pro. Reporter 2025.07.22
47 44 Williams County Grading Permit
Other
2 Basin Electric Power Cooperative Erin Fox Dukart 2025.08.06
48 48 Preconstruction Minutes and Notice of Intent to Start Construction
Other
3 Basin Electric Power Cooperative 2025.08.14
49 49 Return Receipt (2)
Other
2 United States Postal Service 2025.08.13
50 51 Executed Contract
Other
13 Public Service Commission 2025.08.18
51 53 Monthly Construction Report - August 2025
Other
1 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2025.09.04
52 54 Topsoil Inspection Report
Other
13 Stantec Consulting Services Inc. 2025.09.08
53 55 Monthly Construction Report - September 2025
Other
1 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2025.10.08
54 56 Monthly Construction Report - October 2025
Other
1 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2025.11.06
55 57 Monthly Construction Report - November 2025
Other
1 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2025.12.04
56 58 Monthly Construction Report - December 2025
Other
1 Basin Electric Power Cooperative Ryan King, Environmental Coordinator 2026.01.07
57 2 Receipt# 12,309 $100,000.00 Application Fee
Receipt
1 Basin Electric Power Cooperative 2025.03.10
58 3 Receipt# 12,310 $50,000.00 Siting Admin Fee
Receipt
1 Basin Electric Power Cooperative 2025.03.10

Back to Top ↑

Event History:

1
Rows
Event Date & Time
1 Formal Hearing 2025.06.30 09:00 am