56 Rows |
Docket Number |
Description & Type |
Page Count |
On Behalf Of |
Filed By |
Date Filed |
| 1 |
1 |
Consolidated Application for Certificate of Corridor Compatibility and Route Permit
Application
|
549 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.03.03 |
| 2 |
2 |
Notification of Application
Other
|
2 |
Public Service Commission |
Adam Renfandt |
2022.03.08 |
| 3 |
3 |
Affidavit of Service by Certified Mail - Notification of Application
Affidavit
|
3 |
Public Service Commission |
|
2022.03.08 |
| 4 |
4 |
Request for Information
Letter
|
2 |
Public Service Commission Staff |
Adam Renfandt |
2022.03.08 |
| 5 |
5 |
Receipt# 11,161 $17,750.00 Application Fee
Receipt
|
1 |
Diamond Resources Co. |
|
2022.03.09 |
| 6 |
6 |
Receipt# 11,162 $355.00 Siting Admin Fee
Receipt
|
1 |
Fredrikson & Byron P.A. |
|
2022.03.09 |
| 7 |
7 |
Siting Admin Fee
Other
|
2 |
Public Service Commission |
|
2022.03.09 |
| 8 |
8 |
Return receipts (3)
Other
|
6 |
United States Postal Service |
|
2022.03.14 |
| 9 |
9 |
Response to 8 March 2022 request for information
Other
|
27 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.03.18 |
| 10 |
10 |
Request for ALJ
Letter
|
3 |
Public Service Commission |
|
2022.03.30 |
| 11 |
11 |
Letter designating ALJ – Hope Hogan
Letter
|
1 |
Office of Administrative Hearings |
Timothy Dawson, Director |
2022.04.01 |
| 12 |
12 |
Request for Information
Letter
|
2 |
Public Service Commission |
Adam Renfandt |
2022.04.08 |
| 13 |
13 |
Commission motion to issue a Notice of Filing and Public Hearing
Motion
|
1 |
Public Service Commission |
|
2022.05.04 |
| 14 |
14 |
Notice of Filing and Public Hearing
Notice
|
3 |
Public Service Commission |
|
2022.05.04 |
| 15 |
15 |
Affidavit of Service by Certified Mail - Notice of Filing and Public Hearing
Affidavit
|
4 |
Public Service Commission |
|
2022.05.05 |
| 16 |
16 |
Affidavit of Service by Regular and Electronic Mail - Notice of Filing and Public Hearing
Affidavit
|
8 |
Public Service Commission |
|
2022.05.05 |
| 17 |
17 |
Email to/from NDNA re Notice of Filing and Public Hearing
Other
|
3 |
North Dakota Newspaper Association |
|
2022.05.06 |
| 18 |
18 |
Return receipt
Other
|
2 |
United States Postal Service |
|
2022.05.09 |
| 19 |
19 |
Response to 8 April 2022 request for information
Other
|
23 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.05.10 |
| 20 |
20 |
Response to 8 April 2022 request for information
Other
|
12 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.05.20 |
| 21 |
21 |
Letter enclosing Witness and Exhibit lists, Exhibits, hearing recording, and attendance sheet
Letter
|
1 |
Hope Hogan, ALJ - Office of Administrative Hearings |
|
2022.06.08 |
| 22 |
22 |
Witness list
Other
|
1 |
Office of Administrative Hearings |
|
2022.06.08 |
| 23 |
23 |
Exhibit list
Other
|
1 |
Office of Administrative Hearings |
|
2022.06.08 |
| 24 |
24 |
Electronic recording of 6 June 2022 formal hearing
Audio
|
1 |
Office of Administrative Hearings |
|
2022.06.08 |
| 25 |
25 |
Hearing attendance sheet
Other
|
1 |
Office of Administrative Hearings |
|
2022.06.08 |
| 26 |
26 |
Exhibit 1 – Consolidated Siting Application
Exhibit
|
551 |
Continental Resources, Inc. |
|
2022.06.06 |
| 27 |
27 |
Exhibit 2 – Supplemental application information requests
Exhibit
|
65 |
Continental Resources, Inc. |
|
2022.06.06 |
| 28 |
28 |
Setback Waiver
Other
|
2 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.08 |
| 29 |
29 |
Invoice $636.22
Invoice
|
1 |
North Dakota Newspaper Association |
|
2022.06.08 |
| 30 |
30 |
Affidavit of Publication with tear sheets
Other
|
4 |
North Dakota Newspaper Association |
|
2022.06.08 |
| 31 |
31 |
Letter enclosing proposed Order, Tree and Shrub Mitigation, and Certification Relating or Order Provisions
Letter
|
1 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.09 |
| 32 |
32 |
Proposed Findings of Fact, Conclusions of Law and Order
Other
|
8 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.09 |
| 33 |
33 |
Tree and Shrub Mitigation Specifications
Other
|
1 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.09 |
| 34 |
34 |
Certification Relating to Order Provisions Transmission Facility Siting
Other
|
8 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.09 |
| 35 |
35 |
Affidavit of Todd Hartleben, Redline and Clean Avoidance Area Table
Other
|
7 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.06.22 |
| 36 |
36 |
Commission motion to adopt the Findings of Fact, Conclusions of Law and Order
Motion
|
1 |
Public Service Commission |
|
2022.07.06 |
| 37 |
37 |
Findings of Fact, Conclusions of Law and Order
Order
|
19 |
Public Service Commission |
|
2022.07.06 |
| 38 |
38 |
Affidavit of Service by Certified Mail - Findings of Fact, Conclusions of Law and Order
Affidavit
|
20 |
Public Service Commission |
|
2022.07.06 |
| 39 |
39 |
Letter closing OAH file
Letter
|
1 |
Hope Hogan, ALJ - Office of Administrative Hearings |
|
2022.07.11 |
| 40 |
40 |
Letter - Additional Application Fees
Letter
|
1 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.07.13 |
| 41 |
41 |
Return receipt
Other
|
2 |
United States Postal Service |
|
2022.07.13 |
| 42 |
42 |
Receipt# 11,316 $15,000.00 Additional Application Fee
Receipt
|
1 |
Diamond Resources Co. |
|
2022.07.15 |
| 43 |
43 |
Executed Contract
Other
|
16 |
Public Service Commission |
Adam Renfandt, Analyst |
2022.07.19 |
| 44 |
44 |
Letter enclosing executed contract
Letter
|
16 |
Public Service Commission |
|
2022.07.20 |
| 45 |
45 |
Preconstruction Conference Minutes
Other
|
2 |
Continental Resources, Inc. |
|
2022.07.20 |
| 46 |
46 |
Commission motion to acknowledge the additional $15,000 application fee
Motion
|
1 |
Public Service Commission |
|
2022.07.27 |
| 47 |
47 |
Letter enclosing Commission motion - acknowledging additional $15,000 application fee
Letter
|
2 |
Public Service Commission |
|
2022.07.28 |
| 48 |
48 |
Certification and documentation for route adjustment under section N.D.C.C.49-22.1-15(3)
Other
|
4 |
Continental Resources, Inc. |
|
2022.08.02 |
| 49 |
49 |
Request for Information regarding Certification - docket No. 48
Letter
|
1 |
Public Service Commission |
Adam Renfandt |
2022.08.03 |
| 50 |
50 |
Response to 3 Aug. 2022 Request for Information regarding Certification
Other
|
5 |
Continental Resources, Inc. |
Lawrence Bender, Fredrikson&Byron, P.A. |
2022.08.04 |
| 51 |
51 |
Letter ACK Certification - docket No. 50
Letter
|
1 |
Public Service Commission |
Adam Renfandt |
2022.08.05 |
| 52 |
52 |
Topsoil Inspection Report
Other
|
4 |
Keitu Engineers & Consultants, Inc. |
|
2022.08.29 |
| 53 |
53 |
As-Built Inspection Report- Buddy Domindgo Pipeline
Other
|
22 |
Keitu Engineers & Consultants, Inc. |
|
2023.05.31 |
| 54 |
54 |
Request for Information
Letter
|
2 |
Public Service Commission |
Adam Renfandt |
2023.06.01 |
| 55 |
55 |
Survey Plat Drawings
Other
|
8 |
Continental Resources, Inc. |
Jared Weingartner, P.E. |
2023.06.22 |
| 56 |
56 |
Reclamation and Revegetation Inspection Report
Other
|
12 |
Keitu Engineers & Consultants, Inc. |
Jaimee Antognazzi, CSP |
2024.07.22 |