Case PU-20-018 Detail

01/10/2020

Pump Station Additions - McKenzie & Dunn Counties
Siting Application
Pipeline

Entities:

ONEOK Bakken Pipeline, L.L.C.

69 Dockets:

[Hide | Show]
69
Rows
Docket
Number
Description & Type Page
Count
On Behalf Of Filed By Date
Filed
1 1 Application for Amendment to Corridor Certificate and Route Permit with Waiver
Application
123 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2020.01.10
2 2 Notice of Appearance - Wade Mann & Casey Furey
Other
1 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2020.01.10
3 3 Request for information
Letter
2 Public Service Commission Staff Victor Schock 2020.01.24
4 4 Receipt# 10,465 $100,000.00 Bear Creek Pump Station
Receipt
1 ONEOK Bakken Pipeline LLC 2020.01.27
5 5 Response to 24 Jan. 2020 request for information
Other
7 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2020.02.10
6 6 Letter enclosing agency correspondence
Other
12 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2020.02.13
7 7 Affidavit of Service, Cert. Mail - Notification of Application
Other
3 Public Service Commission 2020.02.21
8 8 Return receipt - 7019-0700-0000-6174-3793
Other
2 USPS 2020.03.02
9 9 Return receipt - 7019-0700-0000-6174-3809
Other
2 USPS 2020.03.02
10 10 Commission Motion to deem application complete and issue Notice
Motion
1 Public Service Commission 2020.03.04
11 11 Notice of Opportunity for Hearing
Notice
3 Public Service Commission 2020.03.04
12 12 Affidavit of Service, Cert. Mail - Notice of Opportunity for Hearing
Other
4 Public Service Commission 2020.03.06
13 13 Affidavit of Service, Reg. & Email - Notice of Opportunity for Hearing
Other
8 Public Service Commission 2020.03.06
14 14 E-mails to-from NDNA re publication of Notice of Opportunity for Hearing
Other
2 North Dakota Newspaper Association 2020.03.06
15 15 Return receipt - 7019-0700-0000-6174-3991
Other
2 USPS 2020.03.11
16 16 Invoice No. 9817 $227.82
Invoice
1 North Dakota Newspaper Association 2020.03.24
17 17 Affidavit of Publication with tear sheets
Other
3 North Dakota Newspaper Association 2020.03.24
18 18 Motion for Continuance (of 1 April 2020 Informal Hearing)
Other
4 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2020.03.30
19 19 Response to Motion for Continuance (of 1 April 2020 Informal Hearing)
Letter
1 Public Service Commission John Schuh, General Counsel 2020.03.30
20 20 Agency Correspondence
Letter
2 North Dakota State Water Commission Steven Best, Planner III 2020.04.02
21 21 Letter regarding Informal Hearing
Letter
1 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2020.11.11
22 22 Commission Motion to issue Notice
Motion
1 Public Service Commission 2020.12.02
23 23 Notice of Opportunity for Hearing
Notice
3 Public Service Commission 2020.12.02
24 24 Affidavit of Service, Cert. Mail - Notice of Opportunity for Hearing
Other
4 Public Service Commission 2020.12.03
25 25 Affidavit of Service, Reg. and E-mail - Notice of Opportunity for Hearing
Other
8 Public Service Commission 2020.12.03
26 26 Emails to-from NDNA re publication of Notice
Other
2 North Dakota Newspaper Association 2020.12.03
27 27 Return receipt
Other
2 United States Postal Service 2020.12.09
28 28 Electronic recording of 11 Dec. 2020 Informal Hearing
Audio
1 Public Service Commission 2020.12.11
29 29 Agency correspondence
Other
3 North Dakota Department of Environmental Quality L. David Glatt 2020.12.16
30 30 Response to information requested at 11 Dec. 2020 Informal Hearing
Other
2 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2020.12.22
31 31 Proposed Findings of Fact, Conclusions of Law and Order
Other
8 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2020.12.30
32 32 Invoice $367.21
Invoice
1 North Dakota Newspaper Association 2021.01.07
33 33 Affidavit of Publication with tear sheets
Other
4 North Dakota Newspaper Association 2021.01.07
34 34 Certification Relating to Order Provisions – Transmission Facility Siting
Other
9 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2021.01.07
35 35 Supplemental response to information requested at 11 Dec. 2020 Informal Hearing
Other
1 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2021.01.28
36 36 Commission Motion to adopt Findings of Fact, Conclusions of Law and Order
Motion
1 Public Service Commission 2021.02.03
37 37 Findings of Fact, Conclusions of Law and Order
Other
18 Public Service Commission 2021.02.03
38 38 Affidavit of Service by Certified Mail - Findings of Fact, Conclusions of Law and Order
Affidavit
19 Public Service Commission 2021.02.04
39 39 Affidavit of Service by Regular and Electronic Mail - Findings of Fact, Conclusions of Law and Order
Affidavit
23 Public Service Commission 2021.02.04
40 40 Return receipt
Other
2 United States Postal Service 2021.02.08
41 41 Executed Contract
Other
12 Public Service Commission 2021.02.16
42 42 Letter enclosing executed contract
Letter
16 Public Service Commission 2021.02.17
43 43 Sample of Landowner Notification Letter, Conditional Use Permit
Other
3 ONEOK Bakken Pipeline, L.L.C. 2021.02.19
44 44 Preconstruction Conference Call Minutes and Notice of Intent to Commence Construction
Other
3 ONEOK Bakken Pipeline, L.L.C. 2021.02.19
45 45 Agency Correspondence
Letter
2 United States Department of the Interior, Fish and Wildlife Service Drew Becker 2021.02.19
46 46 Email with attachments regarding topsoil segregation
Other
57 ONEOK Bakken Pipeline, L.L.C. Joel Robidoux, Operations Engineer 2021.02.19
47 47 Topsoil Segregation Call Minutes
Other
3 ONEOK Bakken Pipeline, L.L.C. 2021.02.22
48 48 Expedited Request for Authorization for Topsoil Removal
Other
59 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2021.02.22
49 49 Electronic recording of 22 Feb. 2021 Special Commission Meeting
Other
1 Public Service Commission 2021.02.22
50 50 Commission motion to approve the removal of topsoil during the winter using the methods specified in the February 19, 2021 and February 22, 2021 Filings.
Motion
1 Public Service Commission 2021.02.22
51 51 Letter enclosing Commission motion
Letter
2 Public Service Commission 2021.02.22
52 52 Response to FWS 19 Feb. 2021 Agency Correspondence comments
Other
2 ONEOK Bakken Pipeline, L.L.C. Paul Hartzheim, M.S. 2021.03.02
53 53 Temporary Discharges Permit
Other
1 North Dakota Department of Environmental Quality Sarah Waldron Feld 2021.03.02
54 54 Topsoil and Construction Report
Other
17 Sort Elliot Hendrickson Inc. 2021.03.05
55 55 Topsoil and Construction Inspection Report #2
Other
16 Sort Elliot Hendrickson Inc. 2021.03.08
56 56 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 23 March 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.03.25
57 57 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 April 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.04.26
58 58 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 May 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.05.24
59 59 Topsoil Authorization and Dunn County Building Permit
Other
10 ONEOK Bakken Pipeline, L.L.C. Wade Mann, Crowley Fleck, PLLP 2021.05.25
60 60 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 June 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.06.28
61 61 Certification Relating to Modification
Other
4 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2021.07.14
62 62 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 July 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.07.27
63 63 Letter acknowledging certification for route adjustment (docket No. 61)
Letter
1 Public Service Commission Staff Victor Schock 2021.08.17
64 64 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 Aug 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.08.25
65 65 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 24 Sept 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.09.28
66 66 ONEOK Bakken Pipeline, Pump Station Additions Progress Report ending 4 Nov 2021
Progress Report
1 ONEOK Bakken Pipeline, L.L.C. 2021.11.05
67 67 As-Built Construction Inspection and Reclamation Report-Big Gulch
Other
23 Sort Elliot Hendrickson Inc. 2021.12.07
68 68 As-Built map
Other
2 ONEOK Bakken Pipeline, L.L.C. Casey Furey, Crowley Fleck, PLLP 2022.02.03
69 69 Certificate of Liability Insurance Certificate #2025-2026 13
Other
1 SEH - Short Elliot Hendrickson Inc. 2025.12.02

Back to Top ↑

Event History:

3
Rows
Event Date & Time
1 Special Commission Meeting 2021.02.22 01:00 pm
2 Informal Hearing 2020.12.11 01:30 pm
3 Informal Hearing 2020.04.01 01:30 pm